Phases can be added to projects to track specific goals or deliverables related to the project. In Phase Settings, you can edit the phase name, add a description, include a date range, assign departments to the phase, give the phase a weight between 1 and 5, and assign groups.
Phase Weight
You can enter a weight between 1 and 5 to indicate how this phase contributes to the project relative to the other phases. This will impact the project progress calculation. By default, each phase will have the weight of 1.
Groups
Groups can be utilized as a way to categorize phases across all of the projects within a Tracker. One example could be creating groups that correspond to your organization’s mission, values, or strategic goals.